Question: The project management team at Parallel Services is having a debate about how to define tasks in the work breakdown structure (WBS). Ann, the project

The project management team at Parallel Services is having a debate about how to define tasks in the work breakdown structure (WBS). Ann, the project manager, wants to break tasks down into the smallest possible units. For example, she objected to a broad task statement called Develop a training schedule. Instead, she suggested three sub tasks:

(1) Determine availability of training room,

(2) Determine availability of attendees, and

(3) Selects specific dates and training times. Karen, another project team member, disagrees. She feels that the broader task statement is better because it allows more flexibility and will produce the same result.

Karen says that if you break tasks into pieces that are too small, you risk over managing the work and spending more time on monitoring than actually performing the tasks. As a member of the team would you tend to agree more with Ann or Karen? What are the pros and cons of each approach?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

In project management defining tasks within the Work Breakdown Structure WBS is crucial for project organization and clarity The debate between Ann an... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

6095a6a04c57f_26097.pdf

180 KBs PDF File

Word file Icon

6095a6a04c57f_26097.docx

120 KBs Word File

Students Have Also Explored These Related General Management Questions!