The standard number of hours that should have been worked for the output attained is 6,000 direct labor hours and the actual number of direct
The standard number of hours that should have been worked for the output attained is 6,000 direct labor hours and the actual number of direct labor hours worked was 6,300. If the direct labor price variance was $3,150 unfavorable, and the standard rate of pay was $9 per direct labor hour, what was the actual rate of pay for direct labor?
a. $9.00 per direct labor hour
b. $9.50 per direct labor hour
c. $8.50 per direct labor hour
d. $7.50 per direct labor hour
Step by Step Solution
★★★★★
3.53 Rating (150 Votes )
There are 3 Steps involved in it
Step: 1
Labor Price Variance Actual Hours Actual ...
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started