Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the
Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.
Activity | Normal Time | Normal Cost | Crash Time | Crash Cost |
B | 4 days | $6,000 | 3 days | $8,000 |
C | 6 days | $4,000 | 4 days | $6,000 |
| | B; $2,000 |
| | B; $8,000 |
| | C; $1,000 |
| | C; $2,000 |
Step by Step Solution
★★★★★
3.38 Rating (145 Votes )
There are 3 Steps involved in it
Step: 1
Total crash cost of Activities crash cost normal cos...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
6099bc09b142c_29976.pdf
180 KBs PDF File
6099bc09b142c_29976.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started