Question
Xootr LLC is the producer of a high-end, award-winning kick scooter, known as the Xootr (pronounced zooter). The basic Xootr model (known as the Ultra
Xootr LLC is the producer of a high-end, award-winning kick scooter, known as the Xootr (pronounced “zooter”). The basic Xootr model (known as the Ultra Cruz) sells for slightly over $200. The company started production using a three-step assembly process depicted in the preceding figure. Three workers assemble the Xootr. The processing times are 13 minutes/unit for the first worker, 11 minutes/unit for the second worker, and 8 minutes/unit for the third worker. The assembly operation runs for 35 hours per week. The average salary for an assembly worker is $12 per hour. As demand for the Xootr grows, the company needs to change its assembly operations to increase its process capacity. Two experts are consulted for advice. The first expert comments: “As we grow our business, we really have to benefit from our workers specializing in a small set of activities. Right now, our longest processing time is 13 minutes per unit. If Xootr wants to double its process capacity, it should simply take each of the three activities and break them up into two sub activities. That way, six workers can produce a unit every 6.5 minutes.” Another expert, however, disagrees. She observes: “Division of labor leads to frustrating, monotone work for the workers. Instead of having workers specialize in small sub activities, Xootr should do the opposite. Imagine one worker would perform all activities from beginning to end. This would avoid the problem of line balancing and increase the labor utilization. And the workers would see how all pieces come together, providing a more meaningful production experience.
If we have six workers operating this way, we can have even more capacity.” What do you think of the comments of these two experts? Draw a process flow diagram for each of the two expert proposals. For each proposal, compute process capacity, labor utilization, and costs of direct labor, assuming that the processing times in the proposal of the first expert would be cut in half (i.e., it would take 6.5 minutes per unit to do the first set of tasks currently included in activity 1 and another 6.5 minutes per unit to do the second set of tasks). Then, ask yourself what other variables might differ across these two proposals.Step by Step Solution
3.38 Rating (157 Votes )
There are 3 Steps involved in it
Step: 1
Here the problem can be summarized as below which is sequential process and follows assembly line ru...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
6093d4dd542d1_24210.pdf
180 KBs PDF File
6093d4dd542d1_24210.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started