If an activity duration cannot be estimated accurately, we should Use the average estimate in our critical path method Use the worst case estimate in

If an activity duration cannot be estimated accurately, we should

Use the average estimate in our critical path method

Use the worst case estimate in our critical path method

Move away from single point estimates and rely on 2 point (best and worst case) estimates

Move away from single point estimates and rely on a 3 point (best, worst and most likely case) estimates.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Warren R. Plunkett, Gemmy S. Allen

10th edition

1111221340, 978-1111221348

More Books

Students also viewed these General Management questions

Question

Summarize the women's liberation movement.

Answered: 1 week ago