0 1) On your last 3 projects a 3 person crew achieved the following labor production for placing concrete with a bucket and crane.
0 1) On your last 3 projects a 3 person crew achieved the following labor production for placing concrete with a bucket and crane. Proj A Proj B Proj C 500 CY 7 hours 400 CY 8 hours 600 CY 8 hours The cost for the 3 person crew is $50 per hour. What is your estimated cost for a 550 CY pour?