Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

09 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that

image text in transcribed

09 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: At 12-31-2018 At 12-31-2019 At 12-31-2020 Percentage of completion 10% 60% 100% Costs incurred to date $ 350,000 $2,500,000 $4,250,000 Estimated costs to complete 3,150,000 1,700,000-0- Billings to Axelrod, to date 720,000 2,170,000 3,600,000 Required: 1. For each of the three years, prepare a schedule to compute total gross profit or loss to be recognized as a result of this contract. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs. 09 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: At 12-31-2018 At 12-31-2019 At 12-31-2020 Percentage of completion 10% 60% 100% Costs incurred to date $ 350,000 $2,500,000 $4,250,000 Estimated costs to complete 3,150,000 1,700,000-0- Billings to Axelrod, to date 720,000 2,170,000 3,600,000 Required: 1. For each of the three years, prepare a schedule to compute total gross profit or loss to be recognized as a result of this contract. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2018 and 2019 as either cost in excess of billings or billings in excess of costs

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Forensic And Investigative Accounting

Authors: D. Larry Crumbley, Lester E. Heitger, G. Stevenson Smith

7th Edition

0808040731, 9780808040736

More Books

Students also viewed these Accounting questions