1 0 - 2 9 COST ESTIMATION, CUMULATIVE AVERAGE - TIME LEARNING CURVE. The Pacific Boat Company, which is under contract to the Royal Canadian

10-29 COST ESTIMATION, CUMULATIVE AVERAGE-TIME LEARNING CURVE. The Pacific
Boat Company, which is under contract to the Royal Canadian Navy, assembles troop deployment boats. As part of its research program, it completes the assembly of the first of a new model (PT109) of deployment boats. The Navy is impressed with the PT109. It requests that Pacific Boat submit a proposal on the cost of producing another six PT109s.
Pacific Boat reports the following cost information for the first PT109 assembled and uses a 90% cumulative average-time learning model as a basis for forecasting direct manufacturing labour-hours for the next six PT109s.(A 90% learning curve means b=-0.152004.)
\table[[,A,B,C,],[1,Direct material cost,$199,000,,],[2,Direct manufacturing labour time for first boat,14,700,labour-hours,],[3,Direct manufacturing labour rate,$,42,per direct manufacturing labour-hour],[4,Variable manufacturing overhead cost,26,per direct manufacturing labour-hour,],[5,Other manufacturing overhead,20%,of direct manufacturing labour costs,],[6,Tooling costs ?3,$279,000,,],[7,Learning curve for manufacturing labour time per boat,90%,cumulative average time ?b,],[8,,,,],[9,Tooling can be reused at no extra cost because all of its cost has been assigned to the first deployment boat,,,],[10,,,,],[11,PUsing the formula (page 398) for a 90% learning curve, b=ln0.9ln2,0.1053610.693147,0.152004,]]
1. Calculate predicted total costs of producing the sixPT109s for the navy. Perform with cumulative learning curve and also the incremental unit time learning model.
2. What is dollar amount of the difference between a. The predicted total costs for producing the six PT109s in requirement 1 and b. The predicted total costs for producing the six PT109s, assuming that there is no learning curve for the direct manufacturing labour? That is for b assume a linera function of units produced and direct manufacturing labour hours.
HINTS ROUND TO 2 decimal places
PART2 difference between methods is $2012987.20
PLEASE ANSWER CORRECTLY CLEARLY AND SPACED OUT.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

College Accounting A Practical Approach Chapters 1-25

Authors: Jeffrey Slater

12th Edition

013277206X, 978-0132772068

More Books

Students also viewed these Accounting questions