Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1 0 A project that has been tested for its feasibility has already incurred market research costs of 5 0 , 0 0 0 .

10 A project that has been tested for its feasibility has already incurred
market research costs of 50,000. The actual cost of the asset is 100,000 and
the project is expected to yield the following returns:
Year 190,000
Year 280,000
Year 370,000
If the discount rate is 12% the NPV of the project will be:
294,000
44,000
140,000
94,000
11. A project has an NPV of 12,632 when a discount rate of 12% is used and
the same project has an NPV of (6,935) when a discount rate of 22% is used,
the actual internal rate of return of the project is:
6.5%
28.5%
16.5%
18.5%
12 A company is considering investing in a machine with a capital cost of
300,000 with a useful life of 4 years. Annual running costs are expected to
amount to 276,000 including straight line depreciation of 70,000 per annum.
It is estimated that the machine can be disposed of at its net book value at the
end of its life.
The capacity of the machine will be 6 million items for the first two years but
this will fall to 5 million items in years 3 and 4. It is estimated that the
company will be able to sell whatever the machine produces. The average
contribution is 60 per 1,000 units. What is the payback period for the
machine?
1.92 years
2.09 years
0.94 years
1.94 years
13. The discount factor used to appraise capital investment decisions is a
measure of:
The opportunity cost of capital of the business
The opportunity cost of capital of all businesses in the same industry
The current inflation rate
The current high street interest rate1. Cost Variance greater than zero implies that
Actual Cost (AC) is more than Earned Value (EV)
Project is over budget
Project is under budget
Cost performance is as per the baseline plan
2. Budget remaining on the project is expressed as
(BAC - AC) or (EAC - AC)
BAC - EV
EAC - PV
BAC - PV
3. CPI greater than one implies that
Project is over budget
Project progress is as per the baseline plan
Actual Cost (AC) is greater than Earned Value (EV)
Project is under budget
4. Cost Variance less than zero implies that
Cost performance is as per the baseline plan
Project is under budget
Project is over budget
Actual Cost (AC) is less than Earned Value (EV)
5. How will you calculate your EAC if the ETC work will be performed at the budgeted rate?
EAC = BAC/CPI
EAC = AC + BAC EV
EAC = AC + Bottom-up ETC
EAC = AC +[(BAC EV)/(CPI x SPI)]
6. A project's current total Earned Value (EV) is $150,000 and the Actual Cost (AC) is $100,000.
What is the Cost Variance (CV) of the project?
CV is 50,000
CV =-50,000
CV is 1.5
CV is -1.5
7. A project manager

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Finance

Authors: Eddie McLaney

11th Edition

1292134402, 9781292134406

More Books

Students also viewed these Finance questions

Question

In Exercises simplify the ratio of factorials. (n + 1)! n!

Answered: 1 week ago

Question

Would I be a more effective student if I spent less time online?

Answered: 1 week ago

Question

What do you think?

Answered: 1 week ago

Question

LO 25-1 What biological and social factors underlie hunger?

Answered: 1 week ago