Answered step by step
Verified Expert Solution
Question
1 Approved Answer
1 0 A project that has been tested for its feasibility has already incurred market research costs of 5 0 , 0 0 0 .
A project that has been tested for its feasibility has already incurred
market research costs of The actual cost of the asset is and
the project is expected to yield the following returns:
Year
Year
Year
If the discount rate is the NPV of the project will be:
A project has an NPV of when a discount rate of is used and
the same project has an NPV of when a discount rate of is used,
the actual internal rate of return of the project is:
A company is considering investing in a machine with a capital cost of
with a useful life of years. Annual running costs are expected to
amount to including straight line depreciation of per annum.
It is estimated that the machine can be disposed of at its net book value at the
end of its life.
The capacity of the machine will be million items for the first two years but
this will fall to million items in years and It is estimated that the
company will be able to sell whatever the machine produces. The average
contribution is per units. What is the payback period for the
machine?
years
years
years
years
The discount factor used to appraise capital investment decisions is a
measure of:
The opportunity cost of capital of the business
The opportunity cost of capital of all businesses in the same industry
The current inflation rate
The current high street interest rate Cost Variance greater than zero implies that
Actual Cost AC is more than Earned Value EV
Project is over budget
Project is under budget
Cost performance is as per the baseline plan
Budget remaining on the project is expressed as
BAC AC or EAC AC
BAC EV
EAC PV
BAC PV
CPI greater than one implies that
Project is over budget
Project progress is as per the baseline plan
Actual Cost AC is greater than Earned Value EV
Project is under budget
Cost Variance less than zero implies that
Cost performance is as per the baseline plan
Project is under budget
Project is over budget
Actual Cost AC is less than Earned Value EV
How will you calculate your EAC if the ETC work will be performed at the budgeted rate?
EAC BACCPI
EAC AC BAC EV
EAC AC Bottomup ETC
EAC AC BAC EVCPI x SPI
A project's current total Earned Value EV is $ and the Actual Cost AC is $
What is the Cost Variance CV of the project?
CV is
CV
CV is
CV is
A project manager
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started