1 0 . Using the data below, schedule the problem in MS Project. Display and print the schedule in a Gantt chart showing the critical

10. Using the data below, schedule the problem in
MS Project. Display and print the schedule in a
Gantt chart showing the critical path and the
predecessors.
WBS ACTIVITY
IMMEDIATE
PREDECESSOR
DURATION
IN WEEKS
1 Operational
definition
1.1 Research
literature
3
1.2 Identify and
define terms
1.11
1.3 Obtain approval
of definition
1.22
2 Target Selection
2.1 Solicit partners
for pilot
2
2.2 Hold brainstorming
meeting
2.12
2.3 Identify characteristics of targets
2.2,3.11
2.4 Obtain approval
of partners
2.3,1.2,3.41
3 Question set
3.1 Identify process
group members
2
3.2 Develop question
set
2.34
3.3 Prototype and
validate
question set
3.23
3.4 Add partners 3.1,2.13
4 Pilot process
4.1 Schedule with
target audience
2.42
4.2 Conduct beta test 3.4,2.42
4.3 Process feedback
from target
audience
4.22
4.4 Conduct pilot 4.32
4.5 Analyze results 4.42

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

12th Edition

840062338, 840062346, 9780840062338, 978-0840062345

More Books

Students also viewed these General Management questions

Question

What is problem escalation?

Answered: 1 week ago