1 1. Strong Construction Company LLC has entered into a contract beginning January 1, 2016, to build a parking complex. It has been estimated that
1
1. Strong Construction Company LLC has entered into a contract beginning January 1, 2016, to build a parking complex. It has been estimated that the complex will cost $6000000 and will take 3 years to construct. The complex will be billed to the purchasing company at $9000000. The following data pertain to the construction period. 2016 2017 2018 Costs to date $2700000||4500000||$6100000 Estimated costs to complete 3300000 1500000 Progress billings to date 2700000 5500000 9000000 Cash collected to date 2400000 5000000 9000000 -0- Instructions (a). Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. (3 Marks) (b). Using the cost-recovery method, compute the estimated gross profit that would be recognized during each year of the construction period. (2 Marks) Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started