Answered step by step
Verified Expert Solution
Question
1 Approved Answer
1 100 pts Calculate the three-point estimates (weighted averages) for the following activity durations: Optimistic (O) Most Likely (ML) Pessimistic (P) Solution Activity 1 5
1 100 pts Calculate the three-point estimates (weighted averages) for the following activity durations: Optimistic (O) Most Likely (ML) Pessimistic (P) Solution Activity 1 5 8 15 Activity 2 6 15 21 Activity 3 1 3 6 Activity 4 20 22 23 Activity 5 12 17 30 Activity 6 43 45 49 Activity 7 73 73 73 Activity 8 25 28 38
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started