1 (20 pts) Pumpkin Company has contracted to build for the city of Peoria a new school. The estimated cost is $7,000,000 and the contract
1 | (20 pts) | ||||||
Pumpkin Company has contracted to build for the city of Peoria a new school. The estimated cost is $7,000,000 | |||||||
and the contract price is $10,000,000. The school took three years to complete as follows: | |||||||
2020 | 2021 | 2022 | |||||
Costs to Date | $3,500,000 | $5,250,000 | $7,250,000 | ||||
Costs to Complete | $3,500,000 | $2,000,000 | $0 | ||||
Amounts Billed to Date | $3,300,000 | $6,700,000 | $10,000,000 | ||||
Collections to Date | $1,300,000 | $5,300,000 | $10,000,000 | ||||
a | Determine using the percentage of completion method the gross profit to be recognized for: |
b | Determine using the completed contract method the gross profit to be recognized for : |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started