Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1. (4 pts) The Schuman Company is looking at funding the following project. To determine if the project will work in the time frame needed,

image text in transcribed

1. (4 pts) The Schuman Company is looking at funding the following project. To determine if the project will work in the time frame needed, the following must be completed. The project tasks and durations have been identified as shown in the following table. 2. Draw the network diagram b. Determine the project length c. Determine the EST, LST, EFT, LFT for the project tasks d. Determine the critical path and the slack for each task Lag Task Duration (days) Predecessors Relationships with predecessor A 5 B in mnn 3 3 D E F 8 UT 5 3 Start to start Finish to start Finish to start Finish to start Finish to start Finish to start Finish to start Finish to finish Finish to start Finish to start Finish to start Finish to start Finish to finish D D E E F G 3 1 NA 2 2 2. (2 pts) Your team determined that a thermoplastic Injection mold machine was needed on an Internal project. Three years ago, on a previous project, a similar machine was purchased for a price of $1800. However, the previous machine had an 18-inch cavity and your team needs a 30-Inch cavity. You found some information that stated the Index value for Injection molders was 210 three years ago and is now 245. The cost capacity factor for these types of machines was determined to be 0.53. What is your estimate for the new Injection mold machine? 1. (4 pts) The Schuman Company is looking at funding the following project. To determine if the project will work in the time frame needed, the following must be completed. The project tasks and durations have been identified as shown in the following table. 2. Draw the network diagram b. Determine the project length c. Determine the EST, LST, EFT, LFT for the project tasks d. Determine the critical path and the slack for each task Lag Task Duration (days) Predecessors Relationships with predecessor A 5 B in mnn 3 3 D E F 8 UT 5 3 Start to start Finish to start Finish to start Finish to start Finish to start Finish to start Finish to start Finish to finish Finish to start Finish to start Finish to start Finish to start Finish to finish D D E E F G 3 1 NA 2 2 2. (2 pts) Your team determined that a thermoplastic Injection mold machine was needed on an Internal project. Three years ago, on a previous project, a similar machine was purchased for a price of $1800. However, the previous machine had an 18-inch cavity and your team needs a 30-Inch cavity. You found some information that stated the Index value for Injection molders was 210 three years ago and is now 245. The cost capacity factor for these types of machines was determined to be 0.53. What is your estimate for the new Injection mold machine

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

MongoDB Applied Design Patterns Practical Use Cases With The Leading NoSQL Database

Authors: Rick Copeland

1st Edition

1449340040, 978-1449340049

More Books

Students also viewed these Databases questions