Question
1. A project has a 60% chance of a $100,000 profit and a 40 percent of a US $100,000 loss. The Expected Monetary Value for
1. A project has a 60% chance of a $100,000 profit and a 40 percent of a US $100,000 loss. The Expected Monetary Value for the project is:
$100,000 profit
$60,000 loss
$ 20,000 profit
$40,000 loss
2. Assuming that the ends of a range of estimates are +/- 3 sigma from the mean, which of the following range estimates involves the LEAST risk?
Answer:
30 days, plus or minus 5 days
22 - 30 days
Optimistic = 26 days, most likely = 30 days, pessimistic = 33 days
Mean of 28 days
3. If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that the risk event will occur during the fourth month of the project?
Answer:
Less than 1 percent
20 percent
60 percent
80 percent
4. An accepted deadline for project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?
Answer:
Additional resources using the contingency fund
Escalation approval to use contingency funding
Team overtime to meet schedule
Corrective action based on causes
5. The risk will be identified during which risk management process(es)?
Answer:
Perform Quantitative Risk Analysis and Identify Risks
Identify Risks and Monitor and Control Risks
Perform Qualitative Risk Analysis and Monitor and Control Risks
Identify Risks
6. What is meant by RACI?
Answer:
Responsible, Accountable, Confirm, Inform
Recommended, Accountable, Consulted, Inform
Responsible, Accountant, Consulted, Inform
Responsible, Accountable, Consulted, Inform
7. Which of the following statement is true about a Program?
Answer:
A Program is a group of related projects
A Program is a group of unrelated projects
A Program is a part of a big project
None of the above
8. The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?
Answer:
Performance management
Scope identification
Risk identification
Project team status meeting
9. During a bidder conference, you see that one bidder is your close friend. What should your next step be?
Answer:
You will pass some confidential info to him
You will disclose this relationship to your management
You will resign immediately from the bidding process
You will try not to give the contract to him to prove your integrity
10. If a risk event has a 90 percent chance of occurring, and the consequences will be the US $ 10,000, what does the US $9,000 represent?
Answer:
Risk value
Present value
Expected monetary value
Contingency budget
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started