Question
1 Approved Answer
1. A project is being analyzed with below activities identified. Activities A and B start on day 0. ImmediateDuration Activity Predecessors (days) a. organize layout
1. A project is being analyzed with below activities identified. Activities A and B start on day 0.
ImmediateDuration
ActivityPredecessors(days)
a. organize layout team-3
b. organize modification team-6
c. design personnel jobsa6
d. set machinery in placeb4
e. connect utilitiesc,d7
f. modify conveyor systeme4
g. train personnele5
h. finishing touchesf4
i. run test lotg3
a)Find ES, EF, LS, LF, and Slack values all activities.
b)What is (are) the critical path(s)?
c)What is expected project duration?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started