1. A student has been put in charge of a new garden design. The new design will involve five different activities. Per project management
1. A student has been put in charge of a new garden design. The new design will involve five different activities. Per project management guideline, activities "a" and "b" start on day 0. (a) Draw the network diagram. (b) Calculate ES/EF/LS/LF and Slack for all activities. (c) What is the critical path? Immediate Duration Predecessors (days) AADODO Activity a b a d b e 53235 c.d 7