Question
1) A tracking Gantt chart shows planned and actual project schedule information in a graphical format. Which of the following would NOT be included in
1) Atracking Gantt chartshows planned and actual project schedule information in a graphical format. Which of the following wouldNOTbe included in a tracking Gantt?
Select one:
a) Arrows between predecessors
b) Horizontal activity bars
c) Earned Value d) Slipped milestones
2) Integrated Change Control involves which of the following:
Select one:
a) Influencing the factors that cause changes
b) Determining that a change has occurred
c) Managing actual changes as they occur
d) All of the above
3) How is scope acceptance is most often achieved?
Select one:
a) by vote of the project team
b) through comparison with items in the project charter
c) by measuring the time it takes to complete tasks
d) through customer inspection and sign-off on key deliverables
4) A control chart allows you to determine if a process is in control or not. When a process is out of control, you need to identify the causes and make adjustments.
Select one:
True
False
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started