1. A water supply dam will cost $7 million to build and it will have erosion control costs of $800.000 every 6 years forever. At
1. A water supply dam will cost $7 million to build and it will have erosion control costs of $800.000 every 6 years forever. At an interest rate of 5% per year, the capitalized cost of the dam is closest to: $9 3500 000 $8,310,000 -57,800,000