Question
1. Allocate trimmer town USA's costs to the activity-cost pools and determine the activity rate for each pool. 2. Estimate total cost for the waverly
1. Allocate trimmer town USA's costs to the activity-cost pools and determine the activity rate for each pool.
2. Estimate total cost for the waverly Office Park job. How much would USA trimmer town bid to perform the job?
3. trimmer town USA does 28 landscape designs for its customers each year. Estimate the total cost for the waverly Office park job if trimmer town USA allocated costs of the Landscape Design activity based on the number of landscape designs rather than the number of landscape design-hours. How much would trimmer town USA bid to perform the job? Which cost driver do you prefer for the Landscape Design activity? Why?
4. waverly Office Park asks trimmer town USA to give an estimate for providing its services for a 2-year period. What are the advantages and disadvantages for trimmer town USA to provide a 2-year estimate?
Wages and salaries | $480,000 |
---|---|
Depreciation | 54,000 |
Supplies | 115,000 |
Other overhead | 164,000 |
Total overhead costs | $813,000 |
John
Gibson,
controller of
Trimmer Lawn
USA, has established four activity cost pools and the following budgeted activity for each cost pool:
Activity Cost Pool | Activity Measure | Total Activity for the Year |
---|---|---|
Estimating jobs | Number of job estimates | 100 estimates |
Lawn care | Number of direct labor-hours | 10,000 direct labor-hours |
Landscape design | Number of design hours | 600 design hours |
Other | Facility-sustaining costs that are not allocated to jobs | Not applicable |
Gibson
estimates that
Trimmer Lawn
USA's costs are distributed to the activity-cost pools as follows:
| Estimating Jobs | Lawn Care | Landscape Design | Other | Total |
---|---|---|---|---|---|
Wages and salaries | 5% | 70% | 20% | 5% | 100% |
Depreciation | 15% | 45% | 5% | 35% | 100% |
Supplies | 0% | 100% | 0% | 0% | 100% |
Other overhead | 10% | 45% | 25% | 20% | 100% |
Waverly
Office Park, a new development in a nearby community, has contacted
Trimmer Lawn
USA to provide an estimate on landscape design and annual lawn maintenance. The job is estimated to require a single landscape design requiring
40
design hours in total and
100
direct labor-hours annually.
Trimmer Lawn
USA has a policy of pricing estimates at
150%
of cost.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started