Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

1. Assume a company had no jobs in progress at the beginning of July and no beginning inventories. It started and completed only two jobs

1. Assume a company had no jobs in progress at the beginning of July and no beginning inventories. It started and completed only two jobs during JulyJob Y and Job Z. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information from the month of July is available for the company as a whole and for Jobs Y and Z:

Estimated total fixed manufacturing overhead $ 13,000
Estimated variable manufacturing overhead per direct labor-hour $ 1.00
Estimated total direct labor hours to be worked 2,000
Total actual manufacturing overhead costs incurred $ 12,800

Job Y Job Z
Direct materials $ 13,000 $ 8,000
Direct labor cost $ 21,000 $ 7,500
Actual direct labor hours worked 1,400 500

Assuming Job Z contains 200 units and that the company applies a markup of 60% when establishing its selling prices, the price per unit that it would choose for Job Z is closest to:

rev: 06_09_2020_QC_CS-208650

Multiple Choice

  • $134

  • $144

  • $154

  • $164

2. Assume a company started and completed numerous jobs during Julyone of which was Job Z. The company uses two departmental predetermined overhead rates. The rate in the Machining Department is based on machine-hours and the rate in the Assembly Department is based on direct labor-hours. The following additional information from the month of July is available for the company as a whole and for Jobs Z:

Machining Assembly
Estimated total fixed manufacturing overhead $ 48,000 $ 30,000
Estimated variable manufacturing overhead per machine-hour $ 1.50
Estimated variable manufacturing overhead per direct labor-hour $ 2.00
Estimated total machine-hours to be used 12,000
Estimated total direct labor hours to be worked 10,000

Job Z Machining Assembly
Direct materials $ 650 $ 700
Direct labor $ 200 $ 900
Machine-hours 40
Direct labor-hours 60

What is the total job cost for Job Z?

Multiple Choice

  • $2,890

  • $2,910

  • $2,940

  • $2,970

3. Assume a company started and completed numerous jobs during Julyone of which was Job Z. The company uses two departmental predetermined overhead rates. The rate in the Machining Department is based on machine-hours and the rate in the Assembly Department is based on direct labor-hours. The following additional information from the month of July is available for the company as a whole and for Jobs Z:

Machining Assembly
Estimated total fixed manufacturing overhead $ 48,000 $ 30,000
Estimated variable manufacturing overhead per machine-hour $ 1.50
Estimated variable manufacturing overhead per direct labor-hour $ 2.00
Estimated total machine-hours to be used 12,000
Estimated total direct labor hours to be worked 10,000

Job Z Machining Assembly
Direct materials $ 650 $ 700
Direct labor $ 200 $ 900
Machine-hours 40
Direct labor-hours 60

If Job Z contains 50 units, the unit product cost for Job Z is closest to:

rev: 04_27_2020_QC_CS-208650, 06_15_2020_QC_CS-208650

Garrison 17e Rechecks 2020-06-22

Multiple Choice

  • $58.20

  • $59.10

  • $59.20

  • $59.40

4. A company makes two productsProduct A and B. Data regarding the two products follow:

Direct Labor-Hours per Unit Annual Production
Product A 0.75 20,000 units
Product B 0.50 50,000 units

Additional information is as follows:

  1. Product A requires $15 in direct materials per unit, and Product B requires $8.
  2. The direct labor wage rate is $18 per hour.
  3. The companys activity-based absorption costing system has the following activity cost pools:
Estimated Expected Activity
Activity Cost Pool (and Activity Measures) Overhead Cost Product A Product B Total
Machine setups (number of setups) $ 100,000 100 300 400
Special processing (machine-hours) $ 200,000 2,000 6,000 8,000
General factory (Direct labor-hours) $ 150,000 15,000 25,000 40,000

Using activity-based absorption costing, what is the total manufacturing cost (including direct materials, direct labor, and manufacturing overhead) for Product B?

Multiple Choice

  • $1,168,750

  • $1,125,890

  • $1,085,250

  • $1,220,500

5. Which of the following is a valid approach for calculating the cost of unused capacity?

Multiple Choice

  • (Actual amount of the allocation base Amount of allocation base at capacity) Predetermined overhead rate

  • (Amount of allocation base at capacity Actual amount of the allocation base) Predetermined overhead rate

  • (Amount of allocation base at capacity Actual amount of the allocation base) Predetermined overhead rate

  • (Actual amount of the allocation base Amount of allocation base at capacity) Predetermined overhead rate

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial and Managerial Accounting the basis for business decisions

Authors: Jan Williams, Susan Haka, Mark Bettner, Joseph Carcello

16th edition

978-0078111044

Students also viewed these Accounting questions

Question

Using Gauss-Jordan elimination, invert this matrix ONLY 0 0 0 0 1

Answered: 1 week ago