Question
1. Assume the following information: Actual run time this week 4,500 minutes Machine time available this week 5,250 minutes Actual run rate this week 3.6
1. Assume the following information:
Actual run time this week | 4,500 | minutes |
---|---|---|
Machine time available this week | 5,250 | minutes |
Actual run rate this week | 3.6 | units per minute |
Ideal run rate | 4.0 | units per minute |
Defect-free output this week | 15,000 | units |
Total output this week (including defects) | 16,200 | units |
What is the utilization loss in units?
2. Assume the following information:
Actual run time this week | 4,630 | minutes |
---|---|---|
Machine time available this week | 5,000 | minutes |
Actual run rate this week | 3.6 | units per minute |
Ideal run rate | 4.0 | units per minute |
Defect-free output this week | 15,000 | units |
Total output this week (including defects) | 16,668 | units |
What is the quality loss in units?
3. Assume the following information:
Actual run time this week | ? | minutes |
---|---|---|
Machine time available this week | 5,150 | minutes |
Actual run rate this week | ? | units per minute |
Ideal run rate | 4.0 | units per minute |
Defect-free output this week | 15,000 | units |
Total output this week (including defects) | ? | units |
If the utilization rate is 0.90, then the actual run time this week is closest to:
4. Assume the following information:
Actual run time this week | ? | minutes |
---|---|---|
Machine time available this week | 5,000 | minutes |
Actual run rate this week | ? | units per minute |
Ideal run rate | 4.0 | units per minute |
Defect-free output this week | 15,000 | units |
Total output this week (including defects) | ? | units |
If the efficiency rate is 0.66, then the actual run rate this week is closest to:
5. Assume that a business has decided to include average years of tenure per employee and absenteeism rate as performance measures within its balance scorecard. Which of the following choices reflects managements most likely expectations regarding how these measures should change over time?
Average years of tenure per employee | Absenteeism rate | |
---|---|---|
A) | Increase | Increase |
B) | Increase | Decrease |
C) | Decrease | Increase |
D) | Decrease | Decrease |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started