Question
1. Because the customer is not a member of the performing organization, the customer is not a stakeholder of the project. A. True B. False
1. Because the customer is not a member of the performing organization, the customer is not a stakeholder of the project. A. True B. False 2. Directing and managing project execution involves carrying out the project management plan by performing the activities in it. A. True B. False 3. A project charter typically does not authorize the project manager to use organizational resources to complete the project. A. True B. False 4. A commonsense approach to improving the coordination between project plan development and execution is to follow this simple rule: Those who will do the work should not plan the work. A. True B. False 5. Information from the project charter provides a basis for further defining the project scope. A. TrueB. False 6. A unit of work should appear at only one place in the WBS. A. True B. False 7. Project schedules grow out of the basic documents that initiate a project. A. True B. False 8. It is important that the people who help determine what resources are necessary include people who have experience and expertise in similar projects and with the organization performing the project A. True B. False 9. Quality is a lower priority than project scope, time and cost. A. True B. False 10. Before you can improve risk management, you must understand what risk is. A. True B. False
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started