1. Because you are a future project manager, your friend asks for help in renovating his basement. After planning the requirements, you determine the renovation
1. Because you are a future project manager, your friend asks for help in renovating his basement. After planning the requirements, you determine the renovation will cost $35,000 at completion. You plan for the project duration to be from July 1 to Dec 31st (6 months). On October 1st, you realize the renovation is 20% complete, and has cost $9,250. Assume 5 days working week.
a. What is the total cost of the project? What percent of the work has been done?b. What is the planned value, earned value, actual cost for this table?
EV | PV | AC | |
Cost | |||
Schedule |
c. What is the cost variance and schedule variance?d. What is the CPI and SPI? What is the status of the budget and schedule?
2. Set up database project is being managed by your team. It is supposed to start on March 1 and finish on April 30th at a cost of $120,000. Suppose today is end of day March 25th and after discussion we determine the tasks is 30% complete and we have spent $45,000. Assume 5 days working week.
a. What is the total cost of the project? What percent of the work has been done?b. What is the planned value, earned value, actual cost for this table?
EV | PV | AC | |
Cost | |||
Schedule |
c. What is the cost variance and schedule variance?d. What is the CPI and SPI? What is the status of the budget and schedule?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started