Question
1. Calculate the control charts (UCL, CL, and LCL) for each operator-machine combination separately. this needs to be done for both x-bar (average) and range
1. Calculate the control charts (UCL, CL, and LCL) for each operator-machine combination separately. this needs to be done for both x-bar (average) and range charts. What conclusions can you draw from the charts about each operator-machine combination?
Operator Machine 1
Sample | Observations 1-5 | Xbar Avg of all 5 | Range Max-min | ||||
1 | 0.500 | 0.498 | 0.502 | 0.499 | 0.503 | 0.5004 | 0.005 |
2 | 0.496 | 0.497 | 0.500 | 0.502 | 0.499 | 0.4988 | 0.006 |
3 | 0.504 | 0.503 | 0.503 | 0.496 | 0.495 | 0.5002 | 0.009 |
4 | 0.503 | 0.501 | 0.498 | 0.497 | 0.500 | 0.4998 | 0.006 |
5 | 0.500 | 0.502 | 0.503 | 0.498 | 0.495 | 0.4996 | 0.008 |
6 | 0.505 | 0.496 | 0.504 | 0.503 | 0.502 | 0.502 | 0.009 |
Totals: | 0.5001 | 0.0072 |
Operator Machine 2
Sample | Observations 1-5 | Xbar Avg of all 5 | Range Max-min | ||||
1 | 0.495 | 0.497 | 0.495 | 0.502 | 0.500 | 0.4978 | 0.007 |
2 | 0.505 | 0.510 | 0.503 | 0.511 | 0.504 | 0.5066 | 0.008 |
3 | 0.504 | 0.503 | 0.502 | 0.502 | 0.501 | 0.5024 | 0.003 |
4 | 0.500 | 0.501 | 0.497 | 0.496 | 0.504 | 0.4996 | 0.008 |
5 | 0.501 | 0.512 | 0.510 | 0.508 | 0.504 | 0.5070 | 0.011 |
6 | 0.503 | 0.500 | 0.497 | 0.496 | 0.504 | 0.5000 | 0.008 |
Totals: | 0.5022 | 0.0075 |
2.What should be done based on the calculations from question 1?
3.What is the process capability for each operator-machine capability?
4. Can you be sure that every part produced by in-control processes will meet the specification?
5. Identify and explain any underlying assumptions for the calculations done here.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started