1. Calculate the process cycle efficiency of loading almonds on a truck if it takes 20 days to load one almond truck from start to
1.
Calculate the process cycle efficiency of loading almonds on a truck if it takes 20 days to load one almond truck from start to finish and value-added time is only 10 hrs. (Clearly state your assumptions for working hr/day and working days in a week.). Is the PCE world class? Why?