Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1. Chiemsee Knee Replacement Clinic The Chiemsee Knee Replacement Clinic (CKRC) is a sports clinic located at the northern edge of the German Alps. It

1.

Chiemsee Knee Replacement Clinic

The Chiemsee Knee Replacement Clinic (CKRC) is a sports clinic located at the northern edge of the German Alps. It specializes in knee replacements for skiers who come to CKRC from Germany, Austria, Switzerland, and Italy. The clinic currently has one operating room (OR). However, since the clinic has dramatically more demand than capacity, the management team contemplates investing in a second OR. A lean consulting firm, however, suggests that before going ahead with installing new capacity, the clinic should first look at how it uses its existing capacity. The data collected by the consulting firm reveal that:

  • The OR is available for 12 hours a day; the hospital has decided to not perform any procedures between 7pm and 7am. This time is equally divided across three surgeons.
  • The standard procedure time for the knee surgery done at the clinic is 1h.
  • The cleaning and housekeeping that needs to happen after each procedure takes 20 minutes. Almost all of this time could be saved if the cleaning crew were notified earlier on.
  • 10 minutes are spent on patient preparation / anesthesia work before each procedure. (Note: this is not part of the 60-minute procedure time). Proposals have been evaluated to move these 10 minutes to outside the OR, and there exists no medical reason that would prohibit doing this.)
  • A surgeon only starts a case if all of the work associated with the case (preparation, procedure, and cleaning) can be completed in the 4h allotted to each surgeon. Surgeons never start BEFORE their allotted time.
  • Though the clinic aims to operate 7 days a week, holidays, vacation, and construction time lead to an average of one day a week that the OR cannot be used at all.

1- How many cases are going through the OR per day on the days when the OR is in use?

2-What is the OEE of the operating room? Assume a 12h window in which the OR could be used. ?

12 Tasks to 4 Workers

Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise.

Time to Complete Task (seconds):

  • Task 1: 30
  • Task 2: 25
  • Task 3: 15
  • Task 4: 20
  • Task 5: 15
  • Task 6: 20
  • Task 7: 50
  • Task 8: 15
  • Task 9: 20
  • Task 10: 25
  • Task 11: 15
  • Task 12: 20

The current conveyor-paced assembly-line configuration assigns the workers in the following way:

Worker 1: Tasks 1, 2, 3

Worker 2: Tasks 4, 5, 6

Worker 3: Tasks 7, 8, 9

Worker 4: Tasks 10, 11, 12

1- What is the capacity of the current line (in units per hour)?

2- What is the direct labor content (in seconds per unit)?

3- Assume a demand rate of 20 units per minute. What would be the takt time of the process (in seconds per unit)?

4-Assume a demand rate of 20 units per minute. What would be the target manpower?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Accounting

Authors: Richard Baker, Valdean Lembke, Thomas King, Cynthia Jeffrey

8th Edition

73526916, 978-0073526911

More Books

Students also viewed these Accounting questions