Question
1. Chongyun Company incurred the following costs during the current year: Tax in arrears on land P50,000 Payment for the land 1,000,000 Architect fees 230,000
1. Chongyun Company incurred the following costs during the current year:
Tax in arrears on land | P50,000 |
Payment for the land | 1,000,000 |
Architect fees | 230,000 |
Contract price for factory building | 5,000,000 |
Safety fence around construction site | 35,000 |
Safety inspection on building | 30,000 |
Removal of safety fence after the completion of building | 20,000 |
New fence surrounding the factory | 80,000 |
Driveway, parking bay, and safety lighting | 550,000 |
Trees, shrubs, and other landscaping | 200,000 |
What amount should be recorded as cost of land improvements?
1. Chongyun Company incurred the following costs during the current year:
Tax in arrears on land | P50,000 |
Payment for the land | 1,000,000 |
Architect fees | 230,000 |
Contract price for factory building | 5,000,000 |
Safety fence around construction site | 35,000 |
Safety inspection on building | 30,000 |
Removal of safety fence after the completion of building | 20,000 |
New fence surrounding the factory | 80,000 |
Driveway, parking bay, and safety lighting | 550,000 |
Trees, shrubs, and other landscaping | 200,000 |
What amount should be recorded as cost of land improvements?
P630,000
P750,000
P280,000
P830,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started