1. Consider the following 'Network Diagram Data for a small project, Project Y'. Task Duration Task Dependencies A 3 B 2 C 4 A D
1. Consider the following 'Network Diagram Data for a small project, Project Y'.
Task Duration Task Dependencies A 3 B 2 C 4 A D 2 A E 4 B F 4 B G D, E, H 4 C - 4 F. G J HStep by Step Solution