Question
1) Earned value (EV) is: Select one: a) A measure of work performed b) determined during project initiation c) independent of the rate at which
1) Earned value (EV) is:
Select one:
a) A measure of work performed
b) determined during project initiation
c) independent of the rate at which the team is completing work on the activity to date
2) Which statement is true regarding integrated change control?
Select one:
a) it should be performed during project closing
b) it is best performed during project planning
c) it is usually conducted through project team voting
d) it is the process of identifying, evaluating, and managing changes throughout the project's life cycle
3) Scope creep is:
Select one:
a. the tendency for project scope to level off and stabilize
b. the tendency for project scope to grow bigger and bigger
c. the tendency for project to become less costly due to more work added
d. the tendency for project schedule to shortened
4) You cannot control the scope of a project...
Select one:
a) without hiring additional team members
b) without first having clearly defined the scope and set a scope validation process in place
c) without consulting all stakeholders
d) without revising the charter
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started