1. For a project that has the following cash flow and WACC data, what is the project's NPV? WACC 13.00% Year 0 1 2 3
1. For a project that has the following cash flow and WACC data, what is the project's NPV?
WACC 13.00%
Year 0 1 2 3
Cash Flow -$1000 $500 $500 $500
$184.19
$160.71
$171.55
$146.27
$180.58