Question
1. For which type of contract does the owner provide book of unit costs to use for calculating how much will be paid for the
1. For which type of contract does the owner provide book of unit costs to use for calculating how much will be paid for the work?
Group of answer choices
A. Cost-plus with GMP
B. Cost-plus
C. Unit price
D. Job order contract
2. What type of contract would be best suited for a DBB building project?
Group of answer choices
A. Cost Plus
B. Cost Plus with GMP
C. Lump Sum
D. Unit Prices
3. Owners may sometimes accept a small amount of front-end unbalancing so a contractor can finance the early stages of a project
Group of answer choices
A. True
B. False
4. What is the point at which an owner can typically begin to occupy a building or use it for its intended purpose?
Group of answer choices
A. After final completion
B. When the payment bond is terminated
C. At the end of the warranty period
D. After substantial completion
5. On a unit price contract, the periodic payment amount is determined based on
Group of answer choices
A. the total amount due, divided by the number of weeks the project is expected to take to complete
B. the unit prices originally bid and quantities measured as performed
C. the schedule of values and percentage completion of each pay item
D. the submitted invoices, receipts, and timesheets, plus contractor's fee
6. When might a change by the owner be regarded as a "cardinal" change?
Group of answer choices
A. The change drastically modified the method or sequence of construction
B. The change resulted in necessary time extensions.
C. The change was communicated verbally and not in writing.
D. The change caused the contractor to lose money.
7. A contractor may typically terminate a construction contract for convenience.
Group of answer choices
A. True
B. False
8. Which of the following is/are not a differing site condition? Select all that apply.
Group of answer choices
Normal, bad weather
Unexpected minor price increases
Civil unrest
Owner failure to get a permit
9. An owner should expect higher bids if they accept more of the risk for themself regarding differing site conditions.
Group of answer choices
A. True
B. False
10. The Eichleay formula is used to calculate the
Group of answer choices
A. Amount of home-office overhead associated with a delay on a project
B. Amount of jobsite overhead associated with a delay on a project
C. Amount of delay caused by the owner on a project
D. Amount of delay caused by the contractor on a project
E. Amount of liquidated damages to assess on a project completed late
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started