Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1. For which type of contract does the owner provide book of unit costs to use for calculating how much will be paid for the

1. For which type of contract does the owner provide book of unit costs to use for calculating how much will be paid for the work?

Group of answer choices

A. Cost-plus with GMP

B. Cost-plus

C. Unit price

D. Job order contract

2. What type of contract would be best suited for a DBB building project?

Group of answer choices

A. Cost Plus

B. Cost Plus with GMP

C. Lump Sum

D. Unit Prices

3. Owners may sometimes accept a small amount of front-end unbalancing so a contractor can finance the early stages of a project

Group of answer choices

A. True

B. False

4. What is the point at which an owner can typically begin to occupy a building or use it for its intended purpose?

Group of answer choices

A. After final completion

B. When the payment bond is terminated

C. At the end of the warranty period

D. After substantial completion

5. On a unit price contract, the periodic payment amount is determined based on

Group of answer choices

A. the total amount due, divided by the number of weeks the project is expected to take to complete

B. the unit prices originally bid and quantities measured as performed

C. the schedule of values and percentage completion of each pay item

D. the submitted invoices, receipts, and timesheets, plus contractor's fee

6. When might a change by the owner be regarded as a "cardinal" change?

Group of answer choices

A. The change drastically modified the method or sequence of construction

B. The change resulted in necessary time extensions.

C. The change was communicated verbally and not in writing.

D. The change caused the contractor to lose money.

7. A contractor may typically terminate a construction contract for convenience.

Group of answer choices

A. True

B. False

8. Which of the following is/are not a differing site condition? Select all that apply.

Group of answer choices

Normal, bad weather

Unexpected minor price increases

Civil unrest

Owner failure to get a permit

9. An owner should expect higher bids if they accept more of the risk for themself regarding differing site conditions.

Group of answer choices

A. True

B. False

10. The Eichleay formula is used to calculate the

Group of answer choices

A. Amount of home-office overhead associated with a delay on a project

B. Amount of jobsite overhead associated with a delay on a project

C. Amount of delay caused by the owner on a project

D. Amount of delay caused by the contractor on a project

E. Amount of liquidated damages to assess on a project completed late

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contract Law

Authors: Ewan McKendrick

13th Edition

1352005255, 978-1352005257

More Books

Students also viewed these Law questions