1. Given the following information, calculate the critical ratios, and indicate which activities are on target and which need to be investigated. Comment on the
1. Given the following information, calculate the critical ratios, and indicate which activities are on target and which need to be investigated. Comment on the situation for each of the activities. Actual Scheduled Budgeted Actual Activity Progress Progress 2 days 4 days 1 day 3 days 2 days 6 days 3 days 2 days Cost S40 S30 S50 $25 Cost S35 S40 S70 S25