Question
1 Approved Answer
1. Given the following information, use the critical path method to determine: Tasks Immediate predecessors Time (hours) 0 A B A C A D
1. Given the following information, use the critical path method to determine: Tasks Immediate predecessors Time (hours) 0 A B A C A D B,C E B,C F E G H D,F G 10 20 40 10 20 10 0 a. How long the total process will take. b. Which jobs can be delayed without delaying the early start of any subsequent activity?
Step by Step Solution