1 . Given the project information in the following table, what is the probability of completing the National Holiday Toy project in 9 3 time

1. Given the project information in the following table, what is the probability of completing the National Holiday Toy project in 93 time
Tue Mar 196:43 PM
7)
Act. ID
Description
Predecessor
Optm. (a)
Most likely (m) Pess. (b)
Act time te
Variance b-a/612
Critical
1
Design package
None
6
12
24
2
Design product
1
16
19
28
3
Build package
1
4
7
4
Secure patent
2
24
27
36
5
Build product
2
4I
29
47
6
Paint
3,4,5
4
7
7
Test market
6
13
16
19

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions

Question

Prove a result analogous to

Answered: 1 week ago