Question
1. Green Construction Co. has consistently used the percentage-of-completion method of recognizing revenue. During 2014, Green entered into a fixed-price contract to construct an office
1. Green Construction Co. has consistently used the percentage-of-completion method of recognizing revenue. During 2014, Green entered into a fixed-price contract to construct an office building for $24,000,000. Information relating to the contract is as follows:
At December 31
2014 2015
Percentage of completion 15% 45%
Estimated total cost at completion $18,000,000 $19,200,000
Gross profit recognized (cumulative) 1,200,000 2,880,000
Contract costs incurred during 2015 were ??
1. Green Construction Co. has consistently used the percentage-of-completion method of recognizing revenue. During 2014, Green entered into a fixed-price contract to construct an office building for $24,000,000. Information relating to the contract is as follows:
At December 31
2014 2015
Percentage of completion 15% 45%
Estimated total cost at completion $18,000,000 $19,200,000
Gross profit recognized (cumulative) 1,200,000 2,880,000
Contract costs incurred during 2015 were
a. $5,760,000.
b. $5,940,000.
c. $6,300,000.
d. $8,640,000.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started