The Bend-It Company's Assembly Line 1 builds Blue Widgets. Demand for the Blue Widget is 1,230 units per day and the assembly line operates
The Bend-It Company's Assembly Line 1 builds Blue Widgets. Demand for the Blue Widget is 1,230 units per day and the assembly line operates 16 hours per day. The table below shows the work elements required for building the Blue Widget the task time for each work element expressed in minutes, and their precedence relationships. Using a cycle time of 3.9 minutes, balance the assembly line using the longest task time heuristic. Break any ties using the largest number of followers heuristic. Task A B C D E F G A 1.5 Immediate Predecessor(s) A A B B C, D E, F Task task time B 1 Task Time (minutes) 1.5 1 1.5 3.7 0.6 2.2 2 C 1.5 D 3.7 E 0.6 F 2.2 G 2
Step by Step Solution
★★★★★
3.46 Rating (169 Votes )
There are 3 Steps involved in it
Step: 1
We need to find balance the assembly line using the longest task time heuristic Step 1 We need to ca...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3