1. Howell Co. tena las siguientes cantidades para el primer ao de un contrato de construccin de $7,000,000: Costos reales $2,000,000 Costos estimados para completar:
1. Howell Co. tena las siguientes cantidades para el primer ao de un contrato de construccin de $7,000,000:
Costos reales $2,000,000
Costos estimados para completar: $ 6,000,000
Facturacin de progreso: $ 1,800,000
Efectivo cobrado: $1,500,000
Qu cantidad debera reconocer Howard como ganancia (prdida) bruta utilizando el mtodo de porcentaje de ejecucin?
a. ($1,000,000)
b. ($200,000)
C. $800,000
d. $1,750,000