1 Approved Answer
1. If a project has a zero net present value, then the internal rate of return will be A. less than the discount rate. B.
1. If a project has a zero net present value, then the internal rate of return will be A. less than the discount rate. B. greater than the discount rate. C. equal to the discount rate. D. a negative rate of return.
Step by Step Solution
There are 3 Steps involved in it
Step: 1