1. If SV (Schedule Variance) is positive, is the project: on, ahead, or behind schedule? 2. If CV (Cost Variance) is negative, is the project:
1. If SV (Schedule Variance) is positive, is the project: on, ahead, or behind schedule? 2. If CV (Cost Variance) is negative, is the project: on, under, or over budget? 3. If the SPI (Schedule Performance Index) is less than 1, is the project: on, ahead, or behind schedule? 3. If the CPI (Cost Performance Index) is greater than 1, is the project: on, under, or over budget