Question

1 Approved Answer

1 . In month 9 the following project information is available: actual cost is $ 2 , 0 0 0 , BCWP is $ 2

1. In month 9 the following project information is available: actual cost is $2,000, BCWP is $2,100, and BCWS is $2,400. Compute the SV and CV for the project.
2. On day 51 a project has an BCWP of $600, an actual cost of $650, and a BCWS of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?
3. Based on the following information, calculate SV, CV, and EAC
At the end of the fifth day, your team had completed Door frames installation and spent $600 on door leafs and completed about 40% of the task.
Activities Estimated duration Budgeted cost 12345678910111213
Level 1 Door Frames 3 days $ 600.00 $ 200.00 $ 200.00 $ 200.00
Level 1 Door Leafs 4 days $ 1,000.00 $ 250.00 $ 250.00 $ 250.00 $ 250.00
Level 1 Door Hardware 6 days $ 2,400.00 $ 400.00 $ 400.00 $ 400.00 $ 400.00 $ 400.00 $ 400.00

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Economics And Finance Of Higher Education

Authors: John Weidman, John Yeager

1st Edition

1269912941, 9781269912945

More Books

Students also viewed these General Management questions

Question

How is the NDAA used to shape defense policies indirectly?

Answered: 1 week ago

Question

Peoples understanding of what is being said

Answered: 1 week ago