1. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the
1. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. 2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51 ? 3. Given the following project network and baseline information, complete the form to develop a status report for the project at the end of period 4 and the end of period 8 . From the data you have collected and computed for periods 4 and 8 , what information are you prepared to tell the customer about the status of the project at the end of period 8? End of Perlod 4 End of Perlod 8 Task A B C D E F Cumulative Totals Actual % Complete Finished Finished Finished 25% 33% 0% EV AC 300 2200 1500 PV 400 2400 1500 CV SV
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started