Question
1 Approved Answer
1 _____________ is used to compress the project's duration by increasing the total assignment of critical resources to the scheduled activities. Fast tracking Critical Path
1 _____________ is used to compress the project's duration by increasing the total assignment of critical resources to the scheduled activities. Fast tracking Critical Path Method Precedence Diagram Method Crashing