1. Kuhn Tucker Theorem Problem An electric company is setting up a power plant in a foreign country and it has to plan its capacity.

1. Kuhn Tucker Theorem Problem

An electric company is setting up a power plant in a foreign country and it has to plan its capacity.

The peak period demand for power is given by P1 = 400 - Q1 and the off-peak is given by P2 =

380 - Q2. The variable cost is 20 per unit (paid in both markets) and capacity costs 10 per unit

which is only paid once and is used in both periods.

a. Set up the economic problem of peak-load pricing above by stating what the objective

function and constraints are!

b. Write out the Kuhn-Tucker conditions for this problem!

c. Find the optimal outputs (Q1,Q2) and capacity (K) for this problem!

d. How much of the capacity is paid for by each market (i.e. what are the values of 1 and 2)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Law And The Legal Environment

Authors: Jeffrey F Beatty, Susan S Samuelson

4th Edition

0324303971, 9780324303971

More Books

Students also viewed these Economics questions

Question

4. Analyzing: Breaking something down into its parts.

Answered: 1 week ago

Question

Describe ERP and how it can create efficiency within a business

Answered: 1 week ago

Question

Self-awareness is linked to the businesss results.

Answered: 1 week ago

Question

1. Too reflect on self-management

Answered: 1 week ago

Question

Food supply

Answered: 1 week ago