Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1) Lucy is in charge of planning and coordinating a project. Following is the activity information for this project. Time (weeks) Activity Preceded By Optimistic

1) Lucy is in charge of planning and coordinating a project. Following is the activity information for this project.

Time (weeks)

Activity

Preceded By

Optimistic

Most Likely

Pessimistic

A

--

2

2

4

B

A

8

12

16

C

A

4

8

12

D

B,C

2

4

6

E

B

4

6

8

F

A

2

4

6

G

D

2

4

6

H

G

2

4

6

I

E,F,H

2

2

2

Requested:

a. Construct a precedence diagram.

b. Identify the Critical Path(s) and the expected completion time.

c. What is the probability that the training program can be completed in 26 weeks?

2. Following is a table listing the project activities, sequencing requirements and other relevant information:

Expected Time

Direct Cost

Activity

Preceded By

Regular

Crash

Regular

Crash

A

--

6 days

2 day

$2000

$3800

B

--

12

6

2000

10000

C

A

4

2

1000

4000

D

B, C

10

6

3400

4600

E

D

8

6

2800

3900

F

E

6

2

5000

7600

G

B, C

18

8

16000

19600

H

F, G

6

4

2000

4000

Requested:

a. Construct a network including the Early and Late Start and Finish times.

b. Identify the normal Critical Path(s) and the normal expected completion time.

c. Can the project be crashed to last 18 days? Which activities should be crashed and at what additional cost?

3. Amelia Ltd. makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. The company has orders for 48,000 of these trikes. Current schedules yield the following information.

Requirements

Cost to

Cost to

Component

Plastic

Time

Space

Manufacture

Purchase

Front

12

40

8

16

24

Seat/Frame

16

24

8

12

18

Rear wheel

.20

8

.4

2

6

(each)

Available

100000 320000

60000

The company obviously does not have the resources available to manufacture everything needed for the completion of 24000 tricycles so has gathered purchase information for each component.

Requested:

Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 24000 fully completed tricycles at the minimum cost.

4. A paint supply company makes three styles of Paint Rollers, regular, deluxe and heavy. All of the types of brushes must pass through 3 machines. The different types of brushes have the following contributions to profit per case and require the following times (in hours) at each machine per case:

MODEL Machine 1 Machine 2 Machine 3 Profit Margin

Regular 3 2

3

$20

Deluxe 2 4

4

40

Heavy 4 4

5

70

The company has 56 hours available for machine 1, 80 hours for machine 2 and 120 hours for machine 3.

Requested:

Assuming that the company is interested in maximizing the total profit contribution, write the linear programming model for this problem.

5. A payoff table is given as

s1

s2

s3

d1

250

750

500

d2

300

-250

1200

d3

500

500

600

Requested:

a. What choice should be made by the optimistic decision maker?

b. What choice should be made by the conservative decision maker?

c. What decision should be made under minimal regret?

d. If the probabilities of d1, d2, and d3 are .2, .5, and .3, respectively, then what choice should be made under expected value?

6. For the payoff table below, the decision maker will use P(s1) = .15, P(s2) = .5, and

P(s3) =35

s1

s2

s3

d

1

-5000

1000

10,000

d2

-15,000

-2000

40,000

Requested:

a. What alternative would be chosen according to expected value?

b. For a lottery having a payoff of 40,000 with probability p and -15,000 with probability (1-p), the decision maker expressed

the following indifference probabilities.

Payoff Probability
10,000 .85
1000 .60
-2000 .53
-5000 .50

Let U(40,000) = 10 and U(-15,000) = 0 and find the utility value for each payoff.

c. What alternative would be chosen according to expected utility?

7. A decision maker who is considered to be a risk taker is faced with this set of probabilities and payoffs.

s1

s2

s3

d1

5

10

20

d2

-25

0

50

d3

-50

-10

80

probabilit y

.30

.35

.35

For the lottery p (80) + (1 - p) (-50), this decision maker has assessed the following indifference probabilities.

Payoff Probability

50

.60

20

.35

10

.25

5

.22

0

.20

-10

.18

-25

.10

Requested:

Rank the decision alternatives on the basis of expected value and on the basis of expected utility.

8. Three decision makers have assessed utilities for the problem whose payoff table appears below.

s1

s2

s3

d1

500

100

-400

d2

200

150

100

d3

-100

200

300

probabil ity

.2

.6

.2

Indifference Probability for

Person Pay offA BC

300 .95 .68 .45

200 .94 .64 .32

150 .91 .62 .28

100 .89 .60 .22

-100 .75 .45 .10

Requested:

a.Plot the utility function for each decision maker.

b. Characterize each decision maker's attitude toward risk.

c. Which decision will each person prefer?

9. Burger Prince Restaurant is considering the purchase of a $100,000 fire insurance policy. The fire statistics indicate that in a given year the probability of property damage in a fire is as follows:

Fire ]

Damage

$100,00

0

$75,000

$50,000

$25,000

$10,000

$0

Probability

.006

.002

.004

.003

.005

.980

Requested:

a. If Burger Prince was risk neutral, how much would they be willing to pay for fire insurance?

b. If Burger Prince has the utility values given below, approximately how much would they be willing to pay for fire insurance?

Amount of

$100,0

$75,00

$50,00

$25,00

$10,00

$5,000

$0

Loss

00

0

0

0

0

Utility

0

30

60

85

95

99

100

10. Consider the following linear programming problem

Max 8X + 7Y

s.t. 15X + 5Y< 75

10X + 6Y< 60

X + Y< 8

X ,Y 0

Requested:

a. Use a graph to show each constraint and the feasible region.

b. Identify the optimal solution point on your graph. What are the values of X and Y at the optimal solution?

c. What is the optimal value of the objective function?

Ref: Quantitative Methods for Business (4th Edition) by Donald Waters (z-lib.org)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Algebra

Authors: Margaret Lial, John Hornsby, Terry McGinnis

13th Edition

0134895983, 978-0134895987

More Books

Students also viewed these Mathematics questions

Question

What is the confidence level associated with a confidence interval?

Answered: 1 week ago