1. NET PRESENT VALUE AND PROFITIBILITY INDEX What is the net present value and PI of a project with the following cash flows and a
1. NET PRESENT VALUE AND PROFITIBILITY INDEX What is the net present value and PI of a project with the following cash flows and a required return of 11.3%? Year 0 1 2 3 Cash Flow -$28,900 $12.450 $11,630 $ 2,750 |