1. Problem 11.01 Click here to read the eBook: Net Present Value (NPV) NPV Project L costs $55,000, its expected cash inflows are $14,000 per
1. Problem 11.01 Click here to read the eBook: Net Present Value (NPV) NPV Project L costs $55,000, its expected cash inflows are $14,000 per year for 6 years, and its WACC is 10%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations. Full Book $