Question

1 Approved Answer

1 . Product A is made of two units of B and two units of C . B is made of three units of D

1. Product A is made of two units of B and two units of C. B is made of three units of D and four E. C is made of three units of F and two units of E. Lead times for purchase of each unit are: A takes one week, B takes two weeks, C takes one week. D and E take 2 weeks and F takes 3 weeks. Assume that there is a demand for 75 units of A in week 8. There is on-hand inventory of 30 units of B, and 20 units of C. There is a scheduled receipt of E for 500 units in week three. Assume all items are purchased L4L except for item D which is ordered in multiples of 50, F which is ordered in multiples of 100 and E which is 500
A) Show the bill of materials (product structure tree)
B) Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding And Managing Public Organizations

Authors: Hal G. Rainey

4th Edition

047040292X, 978-0470402924

More Books

Students also viewed these General Management questions

Question

4. Explain the strengths and weaknesses of each approach.

Answered: 1 week ago

Question

3. Identify the methods used within each of the three approaches.

Answered: 1 week ago