Question
1. project is estimated to cost $309,024 and provide annual net cash flows of $58,000 for nine years. Present Value of an Annuity of $1
1.
project is estimated to cost $309,024 and provide annual net cash flows of $58,000 for nine years.
Present Value of an Annuity of $1 at Compound Interest | |||||
Year | 6% | 10% | 12% | 15% | 20% |
1 | 0.943 | 0.909 | 0.893 | 0.870 | 0.833 |
2 | 1.833 | 1.736 | 1.690 | 1.626 | 1.528 |
3 | 2.673 | 2.487 | 2.402 | 2.283 | 2.106 |
4 | 3.465 | 3.170 | 3.037 | 2.855 | 2.589 |
5 | 4.212 | 3.791 | 3.605 | 3.352 | 2.991 |
6 | 4.917 | 4.355 | 4.111 | 3.784 | 3.326 |
7 | 5.582 | 4.868 | 4.564 | 4.160 | 3.605 |
8 | 6.210 | 5.335 | 4.968 | 4.487 | 3.837 |
9 | 6.802 | 5.759 | 5.328 | 4.772 | 4.031 |
10 | 7.360 | 6.145 | 5.650 | 5.019 | 4.192 |
Determine the internal rate of return for this project, using the Present Value of an Annuity of $1 at Compound Interest table shown above. %
2.
-
Project 1 requires an original investment of $73,000. The project will yield cash flows of $18,000 per year for five years. Project 2 has a calculated net present value of $21,100 over a three-year life. Project 1 could be sold at the end of three years for a price of $69,000.
Use the Present Value of $1 at Compound Interest and the Present Value of an Annuity of $1 at Compound Interest tables shown below.
Present Value of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 0.890 0.826 0.797 0.756 0.694 3 0.840 0.751 0.712 0.658 0.579 4 0.792 0.683 0.636 0.572 0.482 5 0.747 0.621 0.567 0.497 0.402 6 0.705 0.564 0.507 0.432 0.335 7 0.665 0.513 0.452 0.376 0.279 8 0.627 0.467 0.404 0.327 0.233 9 0.592 0.424 0.361 0.284 0.194 10 0.558 0.386 0.322 0.247 0.162 Present Value of an Annuity of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 1.833 1.736 1.690 1.626 1.528 3 2.673 2.487 2.402 2.283 2.106 4 3.465 3.170 3.037 2.855 2.589 5 4.212 3.791 3.605 3.352 2.991 6 4.917 4.355 4.111 3.784 3.326 7 5.582 4.868 4.564 4.160 3.605 8 6.210 5.335 4.968 4.487 3.837 9 6.802 5.759 5.328 4.772 4.031 10 7.360 6.145 5.650 5.019 4.192 a. Determine the net present value of Project 1 over a three-year life with residual value, assuming a minimum rate of return of 12%. If required, round to the nearest dollar. $
b. Which project provides the greatest net present value?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started