Question: 1 . Question 1 Imagine you are managing a project that hits a major milestone early, putting the team ahead of schedule. This alters the
Question
Imagine you are managing a project that hits a major milestone early, putting the team ahead of schedule. This alters the project plans original course of action. What is the name for this type of event?
point
A reset
A deviation
A risk
An issue
Question
What should project managers track to ensure the team meets deadlines?
point
Track project successes and celebrate achievements with the team.
Track tasks as they progress and as the project approaches key milestones.
Track costs to avoid over or underspending on project activities.
Track stakeholder engagement to ensure they are aligned on project goals.
Question
Which tool provides an overview of a projects common elements, summarizes them as a snapshot, and communicates project status to the team and stakeholders in a centralized place?
point
Project status report
Burndown chart
Roadmap
Gantt chart
Question
Which tool is most useful near the end of a project, when meeting deadlines is the top priority?
point
Probability and impact matrix
Burndown chart
Roadmap
Gantt chart
Question
A software company builds an application to track employee satisfaction. A contractor delays the completion of a key task. Which of the triple constraints does this change impact the most?
point
Timeline
Scope
Budget
Question
Which of the following items should a project manager include in a change request form for a project team? Select all that apply.
point
Original project proposal
Retrospective summary
Teams involved
Project name
Question
Imagine that a restaurant is moving to a new location and must pass a government health inspection before it can open. What type of dependency is the inspection? Select all that apply.
point
Discretionary dependency
Internal dependency
Mandatory dependency
External dependency
Question
You brainstorm with your team members to identify and list the events that might delay the project. What type of document are you creating in this scenario?
point
Task List
Risk Matrix
Impact Matrix
Risk register
Question
Three team members on your project cannot agree on an implementation for a key task. How can you ensure a decision is made in time?
point
Adjust the timeline for the project due to the delay
Give the team members more time to make a decision
Make a guess to the best of your knowledge and implement
Escalate the question to leadership for feedback
Question
What can project managers do to keep trench war disagreements from bringing projects to a standstill?
point
Rely on the project roadmap
Send an escalation email
Assess risk exposure
Apply the ROAM technique
Question
As a project manager, youre implementing the ROAM technique for a new risk. You work with stakeholders and team members to formulate a plan to lessen the impact the risk will have on the project. Which ROAM category is this risk now in
point
Resolved
Owned
Accepted
Mitigated
Step by Step Solution
There are 3 Steps involved in it